The Strategic Project Manager's Guide by Ir. Dr Peter Kwan - HTML preview
Download the book in PDF, ePub for a complete version.
16
16
2.0 The Design Management and Contract
Administration Stage
- Cost breakdowns of each tender cost item and the overall price
- Master programme
- Leading project manager, engineer and their proposed project team structure
- Similar job references
- Their proposed method of construction statements
- Any domestic subcontractors
- Their opinions on the expected difficulties
- Their financial strength in terms of profit and loss account, annual report and cash flow situations
- Their current workload
17
17
3.0 The Construction Management Stage
4.0 The Operation and maintenance Stage
18
18
_____________________Progress Test 4 ______________ ______________
1. The complete project management process consists of 4 phases, viz; the planning and feasibility phase, the design management and contract administration phases, the site construction management phase and the occupation and maintenance phases. (True/False)
2. When a project team receives the client’s brief, they should:
a) study the brief together
b) evaluate the feasibility of the brief and advise the clients the deliverables.
c) Start working on the conceptual design first and then discuss later.
3. In developing the design, the common way is to forward to the client a few options and let the client choose the preferred design. (True/False)
4. For a large project, once the conceptual design has been approved, the consultant should proceed to the detail design without information on the updated cost and time impact assuming that they are still the same? (True/False)
5. Prior to the contract award, the consultant should be careful for the following:
a) whether the design has been concurred by the client
b) the design has got the most updated cost and time data and the client is aware of the information
c) the client’s funding and cashflow is still available
19
19
6. In preparing the contract, which of the following must be submitted along with the tender?
- One of the common errors in site construction management is:
- unprepared for the site start planning
- no site accommodation
- no contract document on site
- In construction control, the COW/BSI must inspect the site, attend meetings and write up progress reports at least weekly if not daily. (True/False)
- The most difficult part of a hospital project is not only the complicated E&M services but also the medical equipment delivery. (True/False)
- For good project management, the PM should also care about the defects rectification and project review during the defects liability period. (True/False)
